Minister of Regional Development Ivan Shishkov will inspect progress on Sepetember 13 section 3 of Hemus Motorway together with representatives of the Road Infrastructure Agency and the state-owned company "Motorways".
The construction of Hemus Motorway was unfrozen in August after it was suspended due to payment problems for several months.
Most likely, the Echemishka tunnel will be opened today and by 30 September there is an assurance that the Vitinya tunnel will be opened for traffic, Minister Shishkov said.
The builders of lots 1 and 3 of Hemus Motorway have already been paid and more documents are expected from those who are building lot 2. These three sections are expected to be constructed within the agreed timeframe.
Bulgaria Marks National Day of Salvation in Memory of Those Who Died Saving Lives
Bulgarian Orthodox Church Celebrates the Great Christian Feast of the Assumption of the Virgin Mary
Representatives of Bulgaria's Foreign Ministry Spoke with Iva Mihaylova's Mother After Another Court Refusal to Allow Her to Leave North Macedonia for Medical Treatment
Ruse–Varna Road Closed after Crash Involving Two Cars and a Minibus, One Person Killed
Агенция „Митници“ използва нови технологии с изкуствен интелект за разбиване на трафик на дрога